From oil finds to full cycle economics
R. Sinding-Larsen - NTNU, Trondheim - Norway

Topics :

ExxonMobil
Building partnerships in Africa
June 26, 2003


@ ExxonMobil

 

 

 1 - Using a dedicated economics modelling tool - GeoX

    GeoX is a family of knowledge based tools providing an integrated decision support solution for prospectivity and economic analysis of oil investment projects

 2 - The GeoX application model

    Volumetric model :

    • closure
    • thickness
    • net/gross
    • porosity
    • saturation
    • trap fill
    • volume formation
    • %gas
    • recovery factor

    Two levels risk model. Risks of :

    • source rock
    • migration
    • timing
    • reservoir
    • trap
    • accumulation

    HC resources and dry hole risk

    Full cycle prospect valuation :

    • well production rate
    • plateau rate
    • decline rate
    • duration development
    • duration exploration
    • CAPEX
    • OPEX
    • HC prices
    • inflation
    • fiscal regime

    After tax NPV and IRR

 3 - Full Cycle Economic Modelling

  • Well production rate - production capacity of a well
  • Plateau rate - max yearly production capacity
  • Decline rate - % annual decline in production
  • Duration development - time spent to develop the production facilities
  • Duration exploration - time spent before drilling a prospect
  • CAPEX - capital expenditures
  • OPEX - operational expenditures
  • HC prices - anticipated prices during production
  • Inflation - anticipated cost increases during production
  • Fiscal regime - system used to generate government take

 4 - Life cycle model

    • Seismic Acquisition
    • Exploration drilling
    • Appraisal drilling
    • Construction & production drilling
    • Oil production
    • Gas production
    • Disposal

    Timing of operations : seismics, exploration, development, oil & gas production and decommissioning

 5 - The oil production curve

The oil production over time as a result of GeoX simulation

Oil production of the Doba fieldOil production of the Doba field 

 6 - Full Cycle Overall Modelling Framework

  • In : oil resource estimates
  • Expl, Dev & Production
  • Costs & Revenues
  • Corporate Model
  • Out : Cash flow
  • Fiscal Regime
  • Economic Value
  • Out : NPV, IRR, EMV

 7 - Cash flow chronology

The cash flow diagram results from oil pricing and tax draws.

Cash flow diagram for DobaCash flow diagram for Doba 

Compare with the cash flow diagram of a copper mine

Cash flow diagram for copper mine 

 8 - Profitability and risks

Monte Carlo simulation of profitability provided by GeoX

Monte Carlo simulation of profitabilityMonte Carlo simulation of profitability 

Financial risks are inequally distributed through the time cycle of a project !

 

 9 - Oil project decisional diagram

    Exploration : (activities, duration & costs)
    Appraisal, Development, Production : (activities, duration, costs & revenues)

    Events

    • dry : - NPV (exploration C)
    • non-commercial discovery (do not develop) : - NPV (exploration + appraisal C)
    • commercial discovery (develop) : NPV (after tax FC net cash flow)